| Trenching in New Gas Line for Gazebo. (June 3, 2009) Hydro-Vac Holes Identifying Gas, Power & Utility Lines. (June 3, 2009) |
| Main Drainage Outlet. (June 11, 2009) |
| Grading & Packing of Gravel Base Prior to Laying of Asphalt. (June 11, 2009) |
| Laying of Asphalt. Notice the Elevation of the Parking Lot to the Cart Path on the Right Aiding Drainage Flow. (June 11, 2009) |
| Finished Parking Lot and Sewer Pump Out. (June 12, 2009) |
The parking lot was officially completed a few months later when parking stall lines were painted to maximize user space and direct efficient traffic flow. Concrete barriers were also put in place to keep all traffic contained within the parking lot and curtail potential access onto the golf course.